Which of the following Scrum artifacts provides a visual representation of work completed versus work remaining?

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the UCF MAN4583 Project Management Final Exam. Study with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam!

The Burndown Chart serves as a vital Scrum artifact to illustrate the amount of work completed in a sprint against the work remaining over time. It is a graphical representation that enables teams to track their progress towards the sprint goal. The chart typically plots time on the horizontal axis and the remaining work (often measured in story points or hours) on the vertical axis. As work is completed throughout the sprint, the line on the chart should trend downward, ideally reaching zero by the end of the sprint.

This visual tool not only helps the Scrum team monitor their progress but also facilitates communication with stakeholders regarding the current status of the project. By using the Burndown Chart, teams can identify any potential obstacles early, making it easier to adjust their approach to ensure the timely completion of goals.

The other options are essential components of Scrum, but they serve different purposes. The Product Backlog lists the overall project requirements prioritized for development, while the Sprint Backlog consists of items selected for the current sprint along with the tasks required to complete them. The Increment refers to the sum of all the Product Backlog items completed in a sprint, but it does not provide a visual tracking mechanism like the Burndown Chart does. Thus, the Burndown Chart uniquely