Which of the following is NOT a phase in the Scrum methodology for creating specific features?

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the UCF MAN4583 Project Management Final Exam. Study with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam!

In the Scrum methodology, the phases typically involved in creating specific features include planning, reviewing, and adapting, which align with the iterative nature of Scrum. Planning encompasses defining what work will be done in a sprint, reviewing involves assessing what has been completed and what still needs attention, and adapting refers to making necessary adjustments based on feedback and the outcomes of the review.

The absence of "Monitor" as a named phase reflects that while monitoring may be an ongoing activity throughout the Scrum process, it is not formally recognized as one of the core phases. Instead, activities such as assessing progress and performance may take place repeatedly within other phases like reviewing and adapting. This highlights how Scrum focuses on collaboration and iterative improvement rather than strictly linear monitoring processes.