Which document outlines the work to be performed during a sprint?

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the UCF MAN4583 Project Management Final Exam. Study with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam!

The Sprint Backlog is the document that outlines the work to be performed during a sprint. It is a critical artifact in Agile project management, particularly within the Scrum framework. The Sprint Backlog consists of items selected from the Product Backlog, which the team commits to completing during the upcoming sprint. This document not only contains the specific tasks that team members will work on but also prioritizes them based on the sprint goal.

Having a clearly defined Sprint Backlog allows the team to focus on deliverables, ensuring that everyone understands their responsibilities and the scope of work. During the sprint, this document is dynamic and can be updated as the team discovers more about the tasks at hand, fostering an adaptive approach to project management.

In contrast, other options serve different purposes in project management. The Project Charter generally outlines the overall objectives, scope, and stakeholders of the project and does not provide details about specific sprints. The Burndown Chart tracks the remaining work in a sprint and helps to visualize progress over time, while the Product Backlog is a prioritized list of features or requirements for the product as a whole but does not pertain specifically to the tasks for a single sprint.