What is the planned value on day 4 for the project developing 105 job descriptions?

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the UCF MAN4583 Project Management Final Exam. Study with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam!

To determine the planned value on day 4 for a project developing 105 job descriptions, we first need to understand the concept of planned value (PV), which represents the value of work that should have been completed at a specific point in time, according to the schedule.

If the project is a time-bound task, we typically need to know the total budget allocated for the project to calculate the planned value accurately. Assuming we have a specific budget number, planned value can be calculated by determining the proportion of the project that should be completed by day 4.

For example, if the project is to take a certain number of days to complete, we would calculate the required rate of completion per day. After calculating the total budget and the total time estimated for completion, we compare the amount of work completed by day 4 against the planned progress.

If we arrive at the planned value of $10,500 based on this calculation, it suggests that, by day 4, a certain percentage of the total job descriptions was expected to be completed, reflecting a specific budgeted spending. This value accurately aligns with the progress expected based on the project’s timeline, thus indicating it is the planned value at this particular time.

This provides a clear understanding of financial and