What is the earned value on day 4 if the work element is measured using the 0/100 rule?

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the UCF MAN4583 Project Management Final Exam. Study with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam!

To determine the earned value on day 4 using the 0/100 rule, it is essential to understand how this rule applies to project management metrics. The 0/100 rule dictates that a project activity is considered either complete or not complete. Under this method, no earned value is assigned to the activity until it is entirely finished.

If the work element is measured using the 0/100 rule, the earned value reflects the value of the work completed at that point in time. In this scenario, if the work element is still in progress and has not reached completion by day 4, the earned value would correctly be assessed as $0 until the work reaches completion. The reference to a specific earned value number indicates a cumulative monetary value for the completed work up to that point in the project timeline.

However, if the value stated in the response is $4500, this suggests that an interpretation may involve a partial completion of some associated costs or milestone progress leading to earned value calculations that differ from strict adherence to the 0/100 rule, which typically would yield $0. The chosen answer could imply that there was a misunderstanding of the completion status or the valuation processes surrounding parts of the project.

Thus, if the choice is indeed