What is the budget at completion for the project focused on developing 105 job descriptions?

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the UCF MAN4583 Project Management Final Exam. Study with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam!

The budget at completion (BAC) is a crucial metric in project management that represents the total budget allocated for a project once it is fully completed. In the context of the project focused on developing 105 job descriptions, the correct calculation of the BAC would factor in the costs associated with developing each job description and any other associated expenses.

In this scenario, if we assume that the budget for developing each job description is set at a certain amount, it's essential to compute the overall budget based on the number of job descriptions being developed. If developing 105 job descriptions totals $6000, that would indicate that $6000 effectively covers all planned expenditures for the project, including labor, materials, and other overheads necessary to complete the job descriptions.

Therefore, selecting $6000 as the budget at completion aligns with the understanding that it accurately reflects the total resources allocated for the successful completion of the project. The other amounts do not correspond to the established budget or the scope of work required for the project in question.