What is the best risk response if the architect's design may not endure for the intended duration?

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the UCF MAN4583 Project Management Final Exam. Study with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam!

Choosing to avoid risk is particularly appropriate in cases where the potential consequences of that risk could significantly impact the project. If the architect's design is at risk of not enduring for the intended duration, avoiding the risk could involve revising the design or employing materials and techniques that ensure durability. This proactive approach directly addresses the problem and eliminates the risk of failure in the design before it arises.

In project management, avoidance is often the preferred response when a risk could cause severe issues or when there are feasible alternatives. By adjusting project plans or making changes upfront, the project team can prevent adverse outcomes rather than dealing with the repercussions later on.

Other response strategies like accepting or transferring may not sufficiently address the fundamental issue in this scenario. Acceptance would mean acknowledging the risk but not taking action to prevent its occurrence, which could lead to significant problems down the line if the design fails. Transfer would involve shifting the risk to another party, which may not be practical if the design flaws are inherent to the project itself. Mitigation would focus on reducing the impact or likelihood of the risk, but if the design is fundamentally flawed, it may be more effective to avoid the risk entirely rather than just attempt to manage it later.