In a project focusing on job descriptions, if your team is expected to complete 15 per day, how many should be completed by day four?

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the UCF MAN4583 Project Management Final Exam. Study with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam!

To determine how many job descriptions should be completed by day four, it's essential to calculate the daily output in relation to the number of days worked. Since your team is expected to complete 15 job descriptions per day, you would multiply the daily number by the total number of days worked so far.

By day four, the team would have completed:

15 job descriptions/day * 4 days = 60 job descriptions

This calculation indicates that by the end of day four, a total of 60 job descriptions should be finished, making it clear that the correct answer corresponds to this total.

The other options represent different interpretations of daily output or time frames but do not align with the calculation based on the provided daily rate and time period.