During which Agile meeting do the team members define what they will deliver in the next iteration?

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the UCF MAN4583 Project Management Final Exam. Study with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam!

The correct answer is the Sprint Planning Meeting. During this meeting, the Agile team comes together to plan the work for the upcoming iteration, known as a sprint. The primary focus is for the team to prioritize the list of work that needs to be accomplished, identifying what can be realistically delivered in the next iteration based on their capacity and past performance.

In this collaborative setting, team members discuss the user stories or tasks from the product backlog, choose the ones they aim to complete, and define the sprint goal. This meeting sets the foundation for the team’s workflow, clarifying roles and expectations while ensuring that everyone is aligned on what needs to be delivered.

Understanding the other meetings highlights the unique purpose of Sprint Planning: the Sprint Review is focused on evaluating the work completed during the sprint, the Sprint Retrospective addresses how the team can improve processes and teamwork in future sprints, and the Daily Scrum is a short, daily check-in to track progress and adjust plans as needed. Each of these meetings serves different objectives, but none directly addresses the task of defining deliverables for an upcoming iteration like the Sprint Planning Meeting does.